New footpath – Saxton turf carpark interruptions from 17th May – end of May 2022
We would like to inform the NHA community that Fulton Hogan have been engaged by NCC to construct a new concrete footpath outside the hockey turf entrance to the roundabout as per the attached plan.
Their intention is to start this work on Tuesday, 17 May 2022.
Attached for your information is a copy of the traffic management set out.
They will close the road lane closest to the hockey turf and the carparks opposite the turf during the working day. In the evenings and weekends we will open the lane and carparks up again. The road past the hockey turf will be closed to vehicles coming from Suffolk Road end whilst we are on site working.
The project is projected to be completed by the end of May.
Please don’t hesitate to contact me for any extra information you may need.